ELIZABETH LINE VARIOUS SITES

Crossrail System-wide and Tunnel Ventilation System Glanding & Terminating

Project value

£1.8m

Duration

18 months

Client

LB Foster

Tunnel Ventilation System works: DPH completed the dressing in, glanding, terminating & testing of 1,230 cable ends, comprising of power and control cabling, supplying the motor control center, fan control room, dampers, actuators and the fans. These works were completed across 10 stations.

System-wide Trace works: DPH completed the dressing in, glanding, terminating & testing of 2,995 cable ends, comprising of power and control cabling, supplying Tunnel Lighting & Power Panels, tunnel lighting UPS, tunnel led lighting, pushbuttons, pump motor control centers, socket outlets, OHLE switches, cross-passage isolators, cross passage DBs & platform DBs. These works were carried out across 34 stations, shafts and portal locations and 18 cross-passage locations.

Send a Message

Send a Message

Request a Call Back

Related Projects

You May Also Be Interested In:

Related Projects

You May Also Be Interested In: