RENWICK ROAD SIDINGS
Tag & Trace and Installation of submains cabling
Project value
£335,000
Duration
3 weekend possessions
Client
VolkerFitzpatrick
Tag & Trace survey of 14no. cables completed and report produced. Removal of 10no. existing cables and installation (by hand), glanding, terminating & testing of 7no. new cables comprising of 2 core signal asset cabling between LOCs, sub-mains supply cables to points heating transformers and associated bonding. All 7 cables installed, tested and commissioned and redundant cabling removed in a single possession.
In addition to this, 1,178m of 240mm x 4 core SWA was installed using a winch & rollers. Following installation, this cable was jointed, glanded, terminated, tested and brought into use. Cable installed, tested & commissioned and redundant cable removed in a single possession.
















